Heavy duty die casting tool conformal cooling
- heavy duty die casting tool conformal cooling
Die casting tool lead times are typically 6 to 10 weeks and limitations in cycle time drive profitability. High temperatures and pressures require of hot work tool steel.
Solution
- End to end metal AM solution, Metco powder, OAM printing, machining, heat treatment
- Design for AM, internal lattice structures reduce mass
- 1.2344 (H13) material, printed at elevated temperature to mitigate cracking
Impact
- Lead time reduced to 10 days print time + post-processing
- Crack free construction on hard to print alloy
- 28% mass reduction by eliminating unnecessary internal material
- Reduced cycle time with optimized cooling
- Only possible with AM
Further info
Service groups:
Contract manufacturing additive manufacturing
Additive manufacturing metals
Additive manufacturing metals
Application:
Mechanical engineering and automation technology
Focus topic:
Bookmark this service highlight
Your contact person for this service highlight

Ralph Merget
Oerlikon AM
Contact
Phone
+49 1741954706
E-mail